Industry

Equipment for metals and mining

Centrifugal compressors to API 617 rated up to 30 MW, blowers and fans to API 673 up to 5 MW, steam turbines, boiler control systems; high-voltage substation equipment. The 220 kV TsRP substation in Krasnoyarsk, where our specialists took part in the erection and commissioning of the GIS, feeds the Krasnoyarsk aluminium and metallurgical plants. For Nezhinsky GOK the company designed, manufactured and delivered the control systems of two boiler units (2025 contract); in 2026 a contract was signed for their installation supervision and commissioning.

An industrial blower

Industry task → our equipment and services

The tasks of a metallurgical or mining and processing plant with the matching equipment and services; the data are behind the links
Industry taskEquipmentServices
Compressed air, combustion air and aspirationCompressors to API 617 up to 30 MW, blowers and fans to API 673 up to 5 MWCompressor service and repair
Own generation on waste heatSteam turbinesSteam turbine service
Boiler controlBoiler control systemsInstallation supervision and commissioning
Plant power supplyHigh-voltage substation equipment 110–550 kVHigh-voltage equipment service
Vibration and machine conditionInspections and diagnosticsSpare parts

Air and gases for a metals or mining plant: which machines fit

A machine for supplying air or gas is selected primarily on two parameters: the pressure the process needs and the flow it needs. Fans and blowers deliver large flows at a low head; where the pressure must be several times higher than atmospheric, a compressor is required.

Air and gas supply tasks at metals plants and mining and processing plants
TaskWhat the process requiresSuitable machines
Combustion air for furnaces and boilers, aspiration, pneumatic conveyinga large flow at a low head; dust content and gas temperature determine the design of the flow pathcentrifugal blowers and fans to API 673: pressure ratio up to 1.7, flow up to 300,000 Nm³/h, power up to 5 MW
Flotation at a concentratorforced-air (pneumo-mechanical) flotation machines receive air from a blower or fanblowers and fans; the pressure and flow are set by the design of the flotation section
Oxygen, nitrogen and argon for steelmakingan air separation unit: main air compressors and high-capacity nitrogen compressorsintegrally geared compressors to API 617 and API 672 for air and nitrogen: flow up to 160,000 m³/h, power up to 30 MW
Blast furnace blowinga final pressure of 0.46–0.75 MPa at a capacity of about 3,300–7,200 m³/min, the ratings of series-built axial machines with 16–35 MW drivesaxial blast furnace compressors, usually driven by a steam turbine; blowers with a pressure ratio of up to 1.7 are not suitable for this duty

Steam and on-site generation from process gases

Coke oven, blast furnace and basic oxygen furnace gases, once cleaned, are used to raise steam and generate electricity. According to the World Steel Association (worldsteel), these gases can provide more than 60% of the electricity a plant consumes. Steam from boilers fired on these gases and from waste heat boilers drives two classes of turbine:

The turbine type is chosen to suit the plant’s steam balance: a back-pressure or extraction turbine passes steam on to the plant network, while a condensing turbine gets the most power out of steam that has no other use.

Projects

Nezhinsky GOK: control systems for two boiler units

The company is delivering the automation of two Titan M steam boiler units for Nezhinsky GOK, a mining and processing plant in the Republic of Belarus, as a full-cycle project, from engineering solutions to implementation on site. Under a 2025 contract the boiler control systems were designed, manufactured and delivered; in March 2026 the company announced the signing of a contract for their installation supervision and commissioning at the customer’s site.

The team also has experience in steam boiler automation at other sites. For a new boiler at the Knauf Petroboard CHP plant, the specialists designed the control system application software on SIMATIC PCS7, supplied and assembled the cabinets, carried out the factory acceptance tests and worked on commissioning of the control platform. The boiler manufacturer, Belenergomash-BZEM LLC, wrote in its letter of 5 February 2024 that “the engineering and commissioning of the process control system were performed to a consistently high standard of quality”.

The company’s automation work is based on SPPA-T3000, SIMATIC PCS7, TIA Portal and the Russian Ezan control platform with Katren and Sonet controllers; design follows Russian standards.

What a steam boiler control system includes

A boiler control system holds the set load, protects the boiler against dangerous deviations and gives the operator the full picture of its operation. A typical list of control loops for power plant steam boilers with an output of 50 t/h and above is given in the Russian guidelines SO 34.35.101-2003; the protections and shut-off valves are defined by the boiler design and its operating manual.

  • Control loops: fuel flow to the set load, total air to fuel flow with oxygen trim on the flue gas, draught at the top of the furnace, drum level, superheated steam temperature by attemperation, continuous blowdown.
  • Protections and interlocks: fuel shut-off and boiler trip when parameters go beyond permissible limits, and checks of the operating sequence during start-up and shutdown.
  • Monitoring: measurements, alarms, event logging and control from the operator station.

What makes it different

  1. Air

    Machines to API 673 and API 617

    Centrifugal blowers and fans rated up to 5 MW for combustion air to furnaces and boilers, aspiration and pneumatic conveying; for higher pressures, centrifugal compressors to API 617.

  2. Boilers

    Boiler control systems

    Design, control cabinets, factory tests and commissioning; installation supervision of the control systems of two boilers at the Nezhinsky mining plant — under a 2026 contract.

  3. Substation

    Powering a metals plant

    GIS for the 220 kV TsRP substation in Krasnoyarsk, which feeds the aluminium and metallurgical plants: participation in erection and commissioning.

Questions and answers

Which blowers do you supply?

Centrifugal blowers and fans to API 673: pressure ratio up to 1.7, flow up to 300,000 Nm³/h, power up to 5 MW, for air and process gases. They supply combustion air to furnaces and boilers and serve aspiration, pneumatic conveying and process air. For higher pressures, we offer <a class="term-link" href="../glossary/centrifugal-compressor/index.html" title="What is a centrifugal compressor">centrifugal compressors</a> to API 617 rated up to 30 MW.

Do you have experience at mining and processing plants?

Yes: under a 2025 contract the company designed, manufactured and delivered the control systems of two Titan M boiler units at Nezhinsky GOK in the Republic of Belarus, and in 2026 a contract was signed for their <a class="term-link" href="../glossary/installation-supervision/index.html" title="What is installation supervision">installation supervision</a> and commissioning. Details are in the company news.

Do you work with plant substations?

Yes: our specialists took part in the erection and commissioning of the 220 kV <a class="term-link" href="../glossary/gis/index.html" title="What is GIS (gas-insulated switchgear)">GIS</a> (1,920 sets of equipment) at the TsRP substation in Krasnoyarsk, which feeds the Krasnoyarsk aluminium and metallurgical plants.

Are your blowers suitable for blast furnace blowing?

No. The blowers and fans in our range are rated for a pressure ratio of up to 1.7 and a power of up to 5 MW. Blast furnace blowing needs a pressure several times higher than atmospheric and thousands of cubic metres of air per minute: series-built axial blast furnace compressors deliver 0.46–0.75 MPa at about 3,300–7,200 m³/min and are usually driven by steam turbines of 16–35 MW.

What information is needed for an enquiry about a boiler control system?

The boiler type and steam output, steam parameters, fuel and number of burners; the list of measurements, actuators and protections from the boiler manufacturer’s documentation; details of the existing process control system and the platform the new system must connect to. Please also state the scope of work: design and application software, cabinet manufacture, factory acceptance tests, installation supervision and commissioning, in full or in part.

Do you supply spare parts for compressors and steam turbines at metals plants?

Yes, for Siemens Energy and Dresser-Rand compressor trains and steam turbines used in the power, oil and gas, chemical, petrochemical and metals industries. We supply seals, bearings and bearing shells, flow path components, parts of the oil, control and steam distribution systems, and spares for control and vibration monitoring systems, from selection through to delivery. Prices and delivery terms are provided in reply to an enquiry.

CallSend a request