Installation supervision and commissioning of turbines and compressors
Technical support during erection, commissioning and handover of gas and steam turbines, compressors and turbine generators: our site engineer directs the erection contractor, checks compliance with the manufacturer's documentation and takes the machine through to handover. The full start-up cycle runs from incoming inspection to integrated testing. Team record: 11 SGT-800 gas turbine units in Belarus and the Arctic LNG 2 compressors.

Scope
- incoming inspection of the equipment and of completeness against the shipping documents
- directing the contractor's erection work: setting on the foundation, alignment, connection of pipework and cables
- checking compliance with the manufacturer's requirements and recording defects
- checking the auxiliary systems: oil, fuel, cooling, instrumentation and controls
- cold cranking and first firing, setting of protections and governors
- trial starts, reaching rated parameters, integrated testing
- training of the customer's personnel under an agreed programme
- handover into operation with a report and recommendations
Installation supervision, commissioning supervision and commissioning: who is responsible for what
The difference lies in who does the work with their own workforce. Under installation supervision and commissioning supervision, the customer’s erection and commissioning contractors or its own personnel assemble and set up the machine, while the site engineer provides technical direction: sets the sequence of operations according to the manufacturer’s documentation, checks how they are carried out and takes part in accepting each stage. Under commissioning, the commissioning organisation carries out the checks, settings and tests itself. Integrated testing is performed by the customer’s operating personnel with the participation of the contractors and, where necessary, the manufacturer (SP 75.13330.2011, Appendix 1, clause 13).
| Type of work | Who does it | Outcome |
|---|---|---|
| Erection | the erection contractor with its own personnel and plant | no-load individual tests of the machines are completed and the working commission accepts the equipment for integrated testing |
| Installation supervision | a site engineer from the manufacturer or a service company | the machine is assembled to the manufacturer’s documentation, defects are cleared and stages are accepted by certificates |
| Commissioning | the commissioning organisation | protections, governors and the control system are set up; trial starts are completed and the equipment is brought to its design operating mode during integrated testing |
| Commissioning supervision | a site engineer working with the commissioning contractor or the customer’s personnel | starts and settings are performed to the manufacturer’s documentation and engineering decisions are agreed |
Equipment we supervise and commission
The company carries out installation supervision, erection and commissioning work on rotating equipment: gas and steam turbines, turbocompressors, turbine-driven pumps and turbine generators. In its projects it erects and commissions Siemens equipment as well as machines from other Russian and foreign suppliers.
In 2024 three Chinese manufacturers presented the company with certificates of official representative or partner. The certificates were issued with the right to supervise erection and commissioning of these manufacturers’ equipment:
- Qingdao Herui Compressor, 27 June 2024: centrifugal, reciprocating and diaphragm compressors;
- New JCM Group, 28 August 2024: compressor equipment and steam turbines;
- Hangzhou Chinen Turbomachinery, 28 October 2024: HCTC compressors, steam turbines and generators.
More about the certificates is on the company’s partners page. Manufacturer names are given to identify the equipment; trademarks belong to their respective owners.
Stages
- 1
Preparation
Review of the design and the manufacturer's documentation, the schedule and site permits.
- 2
Incoming inspection
Completeness, condition, preservation.
- 3
Installation supervision
Directing erection, alignment, connections.
- 4
Commissioning
System checks, cranking, protection settings, starts.
- 5
Handover
Integrated testing, certificates, personnel training.
Commissioning programme: what it contains
The commissioning programme is the working document for checking, setting up and testing the equipment; it must comply with the manufacturer’s specifications and with occupational safety, fire safety and state supervision requirements. The programme and schedule of integrated testing are drawn up by the customer or, on its instructions, by the commissioning organisation and agreed with the general contractor, the erection contractors and, where necessary, the manufacturer’s supervisory personnel (SP 75.13330.2011, mandatory Appendix 1, clauses 9 and 12).
What the programme usually covers
- scope: the list of machines and systems and the boundaries of each party’s responsibility;
- conditions for starting: erection complete; lubrication, cooling, power supply and control systems set up as far as needed for testing;
- sequence of stages: pre-start checks, individual and functional tests, testing of protections and interlocks, trial starts, governor tuning, integrated testing;
- test methods and acceptance criteria, with values taken from the manufacturer’s documentation and the design: pressures, temperatures, vibration, start-up time;
- modes and duration of integrated testing;
- safety measures, the permit-to-work procedure and the responsible persons of each party;
- forms of test records and certificates, and the work schedule.
The control system can be checked before travelling to site, on a test bench or a model. An example from the company’s practice: testing of the digital model of a 2.4 MW Howden steam turbine has been completed to prepare the unit control system for commissioning. More in the section on digital twins and simulators.
Documents issued on completion
- certificates of installation supervision and commissioning
- test reports and records of protection and governor settings
- a list of erection and operation defects with notes on their clearance
- maintenance recommendations and a plan for the first inspections
Which certificates are signed at each stage
Besides the final certificates, interim documents are signed at every stage of start-up. For process equipment their list is set by SP 75.13330.2011 (mandatory Appendix 2); for power plants the Rules for the Technical Operation of Power Plants and Networks of the Russian Federation (Order of the Russian Ministry of Energy No. 1070 of 4 October 2022) also apply.
| Stage | Document | What it records |
|---|---|---|
| Handover for erection | certificate of handover of the working documentation; certificate of handover of equipment for erection; certificate of foundation readiness | completeness of the documentation, handover of the equipment, readiness of the civil works |
| Erection | certificate of inspection of equipment installation on the foundation, with a record of measurements; certificates of inspection of concealed work | installation in line with the manufacturer’s instructions, permission to grout, concealed work |
| Individual tests | test certificate for machines and mechanisms; certificate of acceptance of equipment after individual tests | duration and result of the test of each machine; readiness for integrated testing, a certificate signed by the working commission |
| Functional tests and trial starts | certificates (records) of functional tests, commissioning records | checks of process and control systems, settings of governors, protections and interlocks |
| Integrated testing | certificate of the results of integrated testing | operation of the equipment under load together with the auxiliary equipment |
| Payment | certificate of services rendered, or form KS-2 certificate of acceptance of work performed and form KS-3 statement of the cost of work performed and expenses | scope and cost of the work |
At power industry facilities the owner may, in the cases provided for, need a temporary permit from the federal state energy supervision authority admitting the facility to operation for commissioning and integrated testing (Rules for the Technical Operation, clause 13; Rules approved by Russian Government Decree No. 85 of 30 January 2021).
Requirements for the customer's site
- the foundation and civil works complete as designed
- lifting equipment and an erection contractor with the required permits
- power supply, compressed air and water for flushing and testing
- site access for the personnel and work permits
- a store for assemblies and spare parts
- communications and a workplace for the engineer with access to the documentation
Installation supervision contract and cost
An installation or commissioning supervision contract sets out where the site engineer’s responsibility ends and that of the erection contractor and the customer begins. It usually specifies:
- the list of equipment and the scope of services: installation supervision, commissioning supervision or commissioning by the contractor’s own engineers;
- the number of specialists, the duration and the working pattern on site, including rotation;
- what the customer provides: site readiness, an erection contractor, lifting equipment, utilities, site access for personnel;
- the procedure for accepting stages, keeping the log and signing certificates;
- how downtime not caused by the contractor and additional work are accounted for.
What determines the cost. The price is calculated for each request once we have studied the equipment and the erection schedule. It depends on:
- the type and number of machines and the extent of the auxiliary systems;
- the format of work: supervision only, or commissioning by our engineers;
- the number of specialists and the time on site;
- the remoteness of the site, logistics and working conditions: the Far North, offshore facilities, work abroad;
- the readiness of the site and documentation: the less downtime, the lower the final cost;
- whether the control system has to be checked before travel, on a test bench or a digital model.
If operating personnel need training during commissioning, say so in the request and we will agree the training programme separately (training of the customer’s personnel).
Projects

Akkuyu NPP: high-voltage testing of 400 kV GIS and SF6 bus ducts
400 kV GIS · 400 kV SF6 bus ducts

Arctic LNG 2: installation and commissioning of feed gas and boil-off gas compressors
feed gas compressors · boil-off gas compressors

Belenergo: installation and commissioning supervision of 11 SGT-800 gas turbine units
11 × SGT-800 · full load in 15 minutes

Ilim: board machine control system in Ust-Ilimsk
board machine of 600,000 tonnes a year · 2023

Knauf Petroboard: CHP steam boiler automation
steam boiler control system on SIMATIC PCS7

Rosseti: GIS for the 220 kV TsRP substation in Krasnoyarsk
1,920 sets of GIS equipment

USC: electrical equipment for three fishing vessels
3 vessels · power distribution and monitoring system based on PMA300 · 2020–2023

Yamal LNG: eight SGT-800 gas turbines, boil-off gas compressors and 29 modular substations
8 × SGT-800 · 4 boil-off gas compressors · 29 modular substations
Installation supervision and commissioning record
Belarus, 11 SGT-800 gas turbine units. In 2023 the company began installation and commissioning supervision of 11 SGT-800 gas turbine units for peaking and standby power sources at Berezovskaya GRES and Minsk CHP-5. By the end of the project installation and commissioning supervision had been completed for all 11 machines; the units can deliver rated output to the grid 15 minutes after a cold start. Maintenance of such machines is described on the SGT gas turbine service page.
Nezhinsky GOK, Belarus. In March 2026 the company signed a contract for installation supervision and commissioning of the control systems of two Titan M boiler units. The company designed, manufactured and delivered these systems under a 2025 contract, so the project is delivered as a full cycle, from engineering solutions to implementation on site (news item on the Nezhinsky GOK contract, 16 March 2026).
Novatek LNG projects. The team’s record includes supply, erection, commissioning and maintenance of eight SGT-800 gas turbines and four boil-off gas compressors at the Yamal LNG plant. At Arctic LNG 2 the previously delivered feed gas and boil-off gas compressors are being erected and commissioned under the direction of the company’s specialists.
The company’s structure includes a quality management and installation supervision group, and the rotating equipment service group has positions for lead site engineers and a commissioning site engineer. The service specialists have been trained at the equipment manufacturers’ plants.
Questions and answers
How does installation supervision differ from erection?
Under installation supervision the erection is done by the customer's contractor, while our engineer directs the work and checks compliance with the manufacturer's documentation: alignment, tightening, connection of the systems. Responsibility for the quality of assembly stays with the erection contractor, and responsibility for the engineering decisions with the site engineer.
What does commissioning cover?
Checking the systems before start-up, cold cranking and first firing, setting the protections and governors, trial starts, reaching rated parameters, integrated testing and handover into operation.
Which documents does the customer receive on completion?
Certificates of <a class="term-link" href="../glossary/installation-supervision/index.html" title="What is installation supervision">installation supervision</a> and commissioning, test and setting records, erection and operation defect lists and maintenance recommendations.
Do you work at sites outside Russia?
Yes: Belarus, Kazakhstan and Uzbekistan; onshore and offshore.
How long does integrated testing of a turbine last?
For most thermal power plant turbines in the power system: at least 72 hours in a row on the grid at the maximum available capacity under current conditions (clause 29 of the Rules approved by Russian Ministry of Energy Order No. 90 of 11 February 2019). Main electrical equipment of power plants and substations must run under load for 72 hours (clause 23 of the Rules for the Technical Operation of Power Plants and Networks). For industrial compressors and mechanical drive turbines, the duration is set by industry acceptance rules and the commissioning programme.
Who draws up the commissioning programme?
The programme and schedule of integrated testing are drawn up by the customer or, on its instructions, by the commissioning organisation. They are agreed with the general contractor and the erection contractors and, where necessary, with the manufacturer’s supervisory personnel (SP 75.13330.2011, Appendix 1, clause 12). Under commissioning supervision the site engineer checks start-up modes, protection settings and acceptance criteria against the manufacturer’s documentation.