Project · Power generation · Belarus
Belenergo: installation and commissioning supervision of 11 SGT-800 gas turbine units

Project data
- Customer
- Belenergo
- Facility
- Beryoza power plant and Minsk CHP-5
- Region
- Belarus
- Industry
- power generation
- Types of work
- installation supervision · commissioning supervision
The task
To create peaking and reserve power sources in the Republic of Belarus that quickly cover load peaks and back up the grid. The fast-start SGT-800 gas turbine units reach full load 15 minutes after a cold start.
The sites and the role of peaking and reserve power sources
A peaking and reserve power source is kept ready to start at all times: it is brought into service during consumption peaks and started quickly if another power source in the grid trips. In Belarus such sources were built at four power plants — the Beryoza and Lukoml power plants, Minsk CHP-5 and Novopolotsk CHP — with a total capacity of 800 MW; their construction was part of the measures to integrate the Belarusian nuclear power plant into the national grid. On 1 July 2024 the Belarusian Ministry of Energy announced that all four sources had been put into operation.
The company provided installation and commissioning supervision at two of the four plants:
| Site | Part of | SGT-800 units | Capacity of the source |
|---|---|---|---|
| Beryoza power plant (Berezovskaya GRES), Beloozersk, Brest Region | RUE Brestenergo | 5 | about 250 MW |
| Minsk CHP-5, Minsk Region | RUE Minskenergo | 6 | 300 MW |
Equipment and services for power plants and CHP plants are described in the Power generation section.
What we did
- Installation supervision
11 SGT-800 gas turbine units
Supervision of the installation of the gas turbine units at the Beryoza power plant and Minsk CHP-5.
- Commissioning supervision
Commissioning work
Supervision of commissioning and of synchronising the units with the grid.
Project timeline
- 2023. The company began installation and commissioning supervision of 11 SGT-800 units at both plants.
- November 2023. The first unit at Minsk CHP-5 was synchronised with the grid under the supervision of the company’s specialists. By then three units at the Beryoza power plant had been connected to the grid under the company’s supervision, and integrated testing of the first stage of the power unit had begun.
- Outcome. Installation and commissioning supervision was completed for all 11 units.
A supervising engineer does not install the equipment themselves: they give technical direction to the installation contractor’s work and check that it complies with the manufacturer’s documentation. Commissioning supervision is the same technical direction at the commissioning stage. The company’s service specialists have been trained at the equipment manufacturers’ works. More details are in the news item on the first SGT-800 units synchronised with the grid and on the Installation supervision and commissioning page.
The result
All 11 SGT-800 gas turbine units have been put into operation as peaking and reserve power sources and reach full load 15 minutes after a cold start.
The SGT-800 in peaking and reserve duty
The SGT-800 is a single-shaft industrial gas turbine made by Siemens Energy, rated at 45.3–62.5 MW depending on the version, with a 15-stage compressor, a three-stage turbine and a DLE (dry low emissions) combustion system. A simple-cycle gas turbine does not have to wait for a heat recovery steam generator and a steam turbine to warm up, so it reaches its output within minutes.
Peaking duty means few operating hours and many starts: according to the turbine manufacturer, each of the four peaking and reserve power sources is designed for 700 operating hours and 350 cold starts a year. The life of such machines is therefore counted in starts as well as in hours: for the SGT-800 the manufacturer offers maintenance based on either time or cycles and states up to 60,000 equivalent operating hours between major overhauls. Inspections and repairs of these machines are covered on the SGT-100 – SGT-800 service page.
Gallery

Equipment and services in this project
Similar projects

Yamal LNG: 8 SGT-800 units and compressors
8 × SGT-800 · 4 boil-off gas compressors · 29 modular substations

Arctic LNG 2: compressor installation and commissioning
feed gas compressors · boil-off gas compressors

Rosseti: GIS for the 220 kV TsRP substation
1920 sets of GIS equipment