Project · Power generation · Belarus

Belenergo: installation and commissioning supervision of 11 SGT-800 gas turbine units

Gas turbine units11× SGT-800 Full load15min after a cold start Sites2Beryoza power plant, Minsk CHP-5 Purposepeaking and reservepower sources
Peaking and reserve power plant in Belarus with gas turbine units

Project data

Customer
Belenergo
Facility
Beryoza power plant and Minsk CHP-5
Region
Belarus
Industry
power generation
Types of work
installation supervision · commissioning supervision

The task

To create peaking and reserve power sources in the Republic of Belarus that quickly cover load peaks and back up the grid. The fast-start SGT-800 gas turbine units reach full load 15 minutes after a cold start.

The sites and the role of peaking and reserve power sources

A peaking and reserve power source is kept ready to start at all times: it is brought into service during consumption peaks and started quickly if another power source in the grid trips. In Belarus such sources were built at four power plants — the Beryoza and Lukoml power plants, Minsk CHP-5 and Novopolotsk CHP — with a total capacity of 800 MW; their construction was part of the measures to integrate the Belarusian nuclear power plant into the national grid. On 1 July 2024 the Belarusian Ministry of Energy announced that all four sources had been put into operation.

The company provided installation and commissioning supervision at two of the four plants:

SGT-800 gas turbine units at the project sites (open data)
SitePart ofSGT-800 unitsCapacity of the source
Beryoza power plant (Berezovskaya GRES), Beloozersk, Brest RegionRUE Brestenergo5about 250 MW
Minsk CHP-5, Minsk RegionRUE Minskenergo6300 MW

Equipment and services for power plants and CHP plants are described in the Power generation section.

What we did

  1. Installation supervision

    11 SGT-800 gas turbine units

    Supervision of the installation of the gas turbine units at the Beryoza power plant and Minsk CHP-5.

  2. Commissioning supervision

    Commissioning work

    Supervision of commissioning and of synchronising the units with the grid.

Project timeline

  1. 2023. The company began installation and commissioning supervision of 11 SGT-800 units at both plants.
  2. November 2023. The first unit at Minsk CHP-5 was synchronised with the grid under the supervision of the company’s specialists. By then three units at the Beryoza power plant had been connected to the grid under the company’s supervision, and integrated testing of the first stage of the power unit had begun.
  3. Outcome. Installation and commissioning supervision was completed for all 11 units.

A supervising engineer does not install the equipment themselves: they give technical direction to the installation contractor’s work and check that it complies with the manufacturer’s documentation. Commissioning supervision is the same technical direction at the commissioning stage. The company’s service specialists have been trained at the equipment manufacturers’ works. More details are in the news item on the first SGT-800 units synchronised with the grid and on the Installation supervision and commissioning page.

The result

All 11 SGT-800 gas turbine units have been put into operation as peaking and reserve power sources and reach full load 15 minutes after a cold start.

The SGT-800 in peaking and reserve duty

The SGT-800 is a single-shaft industrial gas turbine made by Siemens Energy, rated at 45.3–62.5 MW depending on the version, with a 15-stage compressor, a three-stage turbine and a DLE (dry low emissions) combustion system. A simple-cycle gas turbine does not have to wait for a heat recovery steam generator and a steam turbine to warm up, so it reaches its output within minutes.

Peaking duty means few operating hours and many starts: according to the turbine manufacturer, each of the four peaking and reserve power sources is designed for 700 operating hours and 350 cold starts a year. The life of such machines is therefore counted in starts as well as in hours: for the SGT-800 the manufacturer offers maintenance based on either time or cycles and states up to 60,000 equivalent operating hours between major overhauls. Inspections and repairs of these machines are covered on the SGT-100 – SGT-800 service page.

Gas turbine unit of a peaking and reserve power plant
Illustration. Gas turbine unit on site