What is commissioning

Commissioning is the set of checks, adjustments and tests of equipment and control systems after erection and before hand-over to operation. It includes individual tests of components, checks of protection and interlocks, the first start, tuning of operating modes and integrated load trials with hand-over of the equipment to operation.

Key facts

  • Commissioning covers checks, tuning and tests between erection and operation.
  • Stages: pre-commissioning checks, individual tests, protections, first start, integrated trials.
  • Integrated trials usually last 72 hours under load.
  • Work follows an agreed commissioning programme and is documented in reports.
  • Installation supervision and commissioning are usually done by one team.

Stages

Pre-commissioning checks: conformity of the erection to the documentation, flushing and blowing of systems, checks of electrical circuits and instrumentation. Individual tests: running of auxiliaries, trial of the lube oil system, checks of valves and actuators, tests of the control system on the bench and on site. Checks of protection and interlocks with simulated alarms. First start at no load, governor tuning, vibration measurements. Integrated trials — operation under load for a set period (usually 72 hours) with confirmation of performance. Hand-over to operation with as-built documentation.

What is tuned on turbines and compressors

The automatic control and protection system, the speed governor, the compressor anti-surge system, the lube oil and seal gas systems, vibration monitoring, gas turbine combustion by emissions and pulsations, generator synchronisation with the grid. Performance is checked against the data sheet and the contract.

Who takes part

The commissioning contractor or service company with engineers trained at the manufacturer’s plant; the manufacturer’s supervising engineer; the customer’s operating staff, who accept the equipment and are trained during commissioning; where required, representatives of supervisory authorities.

How it differs from installation supervision

Installation supervision ends when the machine is assembled to the documentation; commissioning starts with checks of the assembled machine and ends with its operation under load. In practice one team performs both services: the full cycle from incoming inspection to integrated trials.

Where it appears on this site

Installation supervision and commissioning of turbines and compressors, on-site commissioning of control systems after bench tests, commissioning during control system migration in planned outages; projects — 11 gas turbine units in Belarus, the Arctic LNG 2 compressors, the board machine control system in Ust-Ilimsk, the Knauf Petroboard CHP boiler.

Questions and answers

How long does commissioning take?

It depends on scope and complexity: usually weeks for a single machine and months for a power unit or process line. The final stage is integrated trials under load, as a rule 72 hours of continuous operation. The time is shortened if the control system is tested in advance on a bench or a digital model.

Who signs the commissioning reports?

Individual test reports are signed by representatives of the customer, the erection contractor and the commissioning contractor. The results of integrated trials are accepted by the customer’s working commission. Test and tuning records and as-built documentation are attached to the reports.

Can commissioning be done without stopping production?

For new equipment, yes: it is commissioned before it enters service. When a control system is replaced at an operating plant, the new system is tested on a bench and a digital model and the switchover and tuning are done during a planned outage. See migration to a Russian control platform.

Related terms