Project · LNG · Yamalo-Nenets Autonomous Area

Yamal LNG: eight SGT-800 gas turbines, boil-off gas compressors and 29 modular substations

Gas turbines8× SGT-800 Boil-off gas compressors4 Modular substations29 Locationabove the Arctic Circle
Yamal LNG plant: an LNG tank at night

Project data

Customer
Novatek
Facility
Yamal LNG plant
Region
Sabetta, Yamalo-Nenets Autonomous Area
Industry
LNG
Types of work
supply · installation · commissioning · maintenance

The task

To provide a liquefied natural gas plant with captive power generation and compressor equipment for the process train, and with power distribution across the site — in Far North conditions, above the Arctic Circle, at temperatures down to −50 °C and with a short navigation window for delivering the equipment.

About the facility: the Yamal LNG plant in Sabetta

Yamal LNG is a large-scale Arctic LNG project of Novatek: a plant at Sabetta, in the north-east of the Yamal Peninsula, that liquefies gas from the South Tambey field. The design capacity is 17.4 million tonnes of LNG per year: three process trains of 5.5 million tonnes each and a fourth train of 0.9 million tonnes; the first train started producing LNG on 5 December 2017. The LNG is stored in four tanks of 160,000 m³ each, and a fleet of Arc7 ice-class LNG carriers was built to ship it.

Sabetta is not connected to Russia’s Unified Energy System, so the plant is powered by its own 376 MW gas turbine power station — according to public sources, eight SGT-800 units of 47 MW each. These are the eight turbines of our project.

What we did

  1. Supply · installation · commissioning

    8 SGT-800 gas turbines

    Gas turbine units for the plant’s captive power station.

  2. Supply · installation · commissioning

    4 boil-off gas compressors

    Compressor trains that remove and compress boil-off gas.

  3. Supply · installation · commissioning

    29 modular substations

    Power distribution across the plant site and the infrastructure facilities.

  4. Maintenance

    Service on site

    Our engineers support the operation of the turbines and compressors: inspections, maintenance and advice.

Project equipment and what it does

The project’s three equipment groups work as one chain: the turbines generate electricity, the substations distribute it, and the compressors remove the gas that evaporates from the LNG. At LNG plants, compressed boil-off gas is usually returned to the liquefaction process or sent to the fuel gas system, including that of the power station’s gas turbines.

Yamal LNG equipment our team worked with
EquipmentQuantityWhat matters in operation
SGT-800 gas turbines8in an isolated grid, planned maintenance shutdowns are usually staggered so that the units still running can carry the plant’s load
Boil-off gas compressors4gas evaporates in the tanks and during carrier loading; without its removal, tank pressure would rise until the relief valves lifted
Modular substations with transformers29factory-built modules: the equipment is assembled and tested at the manufacturer’s works, and on site the modules are set in place, connected and commissioned — this reduces the work to be done in Arctic conditions

For all three groups, the team was responsible for supply, installation, commissioning and maintenance. The company has also worked with this turbine model in Belarus, supervising the installation and commissioning of 11 SGT-800 units (the Belenergo project). Service for such machines is described on the SGT gas turbine service and compressor service pages.

The result

The equipment has been handed over into operation and runs as part of the plant. Our engineers continue to work shifts above the Arctic Circle, maintaining the gas turbines and the compressors.

Service above the Arctic Circle

Our engineers’ rotations at the plant follow the resident engineer format: the specialist is permanently based at the customer’s site rather than travelling out on call. A resident engineer monitors the condition and running hours of the machines, takes part in start-ups and shutdowns, plans inspections and is the first to respond to deviations.

At Arctic sites, spare parts are planned in advance: large components arrive by sea, so the stock for turbines and compressors is usually set by running hours and inspection findings, without waiting for a failure.

Work in the gas turbine hall
Illustration. The gas turbine hall
A compressor skid being lifted on site
Illustration. Lifting a compressor skid
Site engineers at an erection site in winter
Illustration. Site engineers on site in winter

Equipment and services in this project

Similar projects

CallSend a request