What is a gas turbine inspection
A gas turbine inspection is a scheduled examination of the machine by operating hours or after an event: a borescope inspection without disassembly, a combustion inspection, a hot gas path inspection with replacement of worn parts, and a major inspection with full disassembly. The result is a report on the condition, the scope of the coming repair and the need for spare parts.
Key facts
- Types: borescope, combustion, hot gas path and major.
- A borescope inspection takes 1–2 days without disassembly.
- Intervals are counted in equivalent hours including starts and fuel.
- Hot gas path at 24–33 thousand hours, major at 48–66 thousand.
- The result is a report of defects, work done and recommendations.
Types of inspection
Borescope — examination of compressor and turbine blades and combustor liners through the standard ports with an endoscope, 1–2 days, without disassembly. Combustion inspection — overhaul of burners, liners and transition pieces. Hot gas path inspection — additionally the vanes and blades of the first stages, replaced by condition. Major inspection — full disassembly, overhaul of the compressor, bearings and rotor, restoration or replacement of parts. Minor inspections by operating hours are carried out in between.
Intervals
Set by the manufacturer in equivalent operating hours allowing for the number of starts, liquid fuel operation and peak loads: typically borescope yearly, combustion at 8–12 thousand hours, hot gas path at 24–33 thousand, major at 48–66 thousand. Diagnostics from vibration, temperatures and emissions allow the dates to be shifted by actual condition.
How it proceeds
Preparation: analysis of operating trends, work plan, ordering of spare parts and tooling. On site: shutdown and cooling, opening, clearance measurements and examination, defect assessment with photographs, part replacement, reassembly, alignment and a trial start with vibration and emission checks. The report lists the defects found, the work done and recommendations until the next inspection.
Where it appears on this site
Inspections and diagnostics of turbines and compressors of 750 kW – 80 MW from seven manufacturers, service of Siemens Energy SGT-600/700/800 gas turbines and Rolls-Royce aeroderivatives, combustion tuning after inspections; the engineers are trained at the manufacturers’ plants.
Questions and answers
What are equivalent operating hours?
A notional running time in which allowances for starts, liquid fuel operation, peak load and trips are added to the actual hours: each such event wears hot parts more than an hour at base load. The conversion rules are set by the turbine manufacturer.
How long does a gas turbine inspection take?
A borescope inspection takes 1–2 days without disassembly. Combustion, hot gas path and major inspections take longer: the duration depends on the model, the scope and spare part availability, so the plan and parts orders are prepared in advance from operating trends.
Can an inspection date be postponed?
Yes, by actual condition: if vibration, temperature and emission diagnostics and a borescope check show no wear, the interval can be extended within the limits allowed by the manufacturer. The decision is supported by a condition report prepared by our inspections and diagnostics team.