Project · LNG · Yamalo-Nenets Autonomous Area
Arctic LNG 2: installation and commissioning of feed gas and boil-off gas compressors
Project data
- Customer
- Novatek
- Facility
- Arctic LNG 2
- Region
- Gydan, Yamalo-Nenets Autonomous Area
- Industry
- LNG
- Types of work
- installation supervision · commissioning
The task
A Novatek gas liquefaction project in a severe climate: three process trains on gravity-based structures and year-round shipments by Arctic-class carriers. The company’s task is to bring the previously supplied feed gas and boil-off gas compressors of the process trains into operation.
The facility: an LNG plant on gravity-based structures
Arctic LNG 2 is another large Novatek natural gas liquefaction project in the Arctic, following Yamal LNG. Its resource base is the Utrenneye field on the Gydan Peninsula. The project provides for three process trains of 6.6 million tonnes of LNG per annum each, 19.8 million tonnes in total.
Each train is a set of topside modules for producing and offloading LNG and stable gas condensate, mounted on a concrete gravity-based structure (GBS) that houses the LNG and condensate storage tanks. The GBS units are built, and the modules installed on them, at the LNG Construction Centre in the Murmansk Region; the completed train is then towed by sea to the Utrenniy terminal. The tow of the first train — the GBS with its topside modules, 330 m long and weighing 640,000 tonnes — took 22 days.
Why a process train needs feed gas and boil-off gas compressors
Feed gas compressors raise the pressure of the gas before liquefaction, while boil-off gas compressors collect the gas that evaporates from the LNG so that it is not lost: the former affect the train’s energy consumption for liquefaction, the latter its product losses.
- Feed gas compressors. The higher the gas pressure at the inlet of the liquefaction unit, the more the gas cools through its own expansion and the less refrigeration the refrigerant cycles have to provide.
- Boil-off gas compressors. Gas evaporates in the storage tanks, which at Arctic LNG 2 are housed in the trains’ gravity-based structures, and while LNG carriers are being loaded. The compressors hold the tank pressure and send the gas to the process or to the plant’s fuel gas system. Capacity is controlled by tank pressure, and centrifugal machines must have anti-surge protection.
What we did
- Installation supervision
Feed gas compressors
Installation of the previously supplied feed gas compressors of the process trains under the supervision of the company’s specialists.
- Installation supervision
Boil-off gas compressors
Installation of the compressors that remove and compress boil-off gas.
- Commissioning
Bringing into operation
Commissioning of the compressor trains, checks of protection and control, loading to the operating point.
Installation supervision of a previously supplied compressor: the typical sequence
Installation supervision and commissioning of a previously supplied compressor follow the manufacturer’s documentation. The general sequence for petroleum, chemical and gas industry facilities is described in API RP 686 (2nd edition, 2009, reaffirmed in 2024):
- Receiving and storage. Completeness and the condition of preservation are checked; components that have waited a long time for installation are inspected before they are set.
- Foundation and grouting. The unit baseplate or soleplates are set to elevation and level, then grouted.
- Piping. Flanges are connected without strain: while the bolts are tightened, shaft movement is monitored with dial indicators at the coupling.
- Shaft train alignment, allowing for thermal growth.
- Oil system. It is flushed to the required cleanliness. If the shafts are sealed with dry gas seals, separation gas is supplied before the lube oil pumps are started, so that oil cannot reach the seals.
- Commissioning. Instrument checks and interlock function tests, trial runs and run-in, then load tests according to the commissioning programme.
The scope of the service and the documents issued on completion are on the installation supervision and commissioning page; maintenance after start-up is covered under compressor service and repair.
The result
Installation and commissioning of the previously supplied feed gas and boil-off gas compressors of the plant’s process trains, under the supervision of the company’s specialists.
Gallery


Equipment and services in this project
Similar projects

Yamal LNG: 8 SGT-800 units and compressors
8 × SGT-800 · 4 boil-off gas compressors · 29 modular substations

Belenergo: 11 SGT-800 gas turbine units
11 × SGT-800 · full load in 15 minutes

Rosseti: GIS for the 220 kV TsRP substation
1920 sets of GIS equipment