Nezhinsky GOK: contract for installation supervision and commissioning of two boiler control systems
Energy Management has signed a contract for installation supervision and commissioning of the control systems of two Titan M boiler units at Nezhinsky GOK in Belarus. The company designed, manufactured and delivered these systems under a 2025 contract. The new contract continues the boiler automation project and moves it to the implementation stage at the customer’s site.

Energy Management has signed a contract for installation supervision and commissioning of the previously delivered control systems of two boiler units at Nezhinsky GOK (mining and processing plant).
The new contract is a logical continuation of the project to create automation systems for the Titan M boilers. The project began with a contract for the design, manufacture and delivery of the control system for two steam boilers at Nezhinsky GOK in the Republic of Belarus; the company announced its signing in June 2025. Moving to the on-site implementation stage means that the company is delivering the full project cycle, from engineering solutions to their implementation at the customer’s facility.
October 2026: integrated tests
The integrated tests have been completed. The Titan M steam boilers, including the control system and utility connections, are ready for operation and heat generation.