Project · Pulp and paper, power generation · Kommunar
Knauf Petroboard: CHP steam boiler automation

Project data
- Mill
- Knauf Petroboard
- Boiler manufacturer
- Belenergomash-BZEM LLC
- Facility
- The mill’s CHP plant, a new steam boiler
- Region
- Kommunar
- Industry
- pulp and paper, power generation
- Types of work
- application software · control cabinets · factory acceptance tests · commissioning
The task
Knauf Petroboard is a board manufacturer in Kommunar, Leningrad Region; the mill’s CHP plant supplies heat to the town and neighbouring plants. The task was to automate a new CHP steam boiler: design the control system application software, build the cabinets and bring the system into operation.
The E-100-3.9-440 GM boiler and its control system
The control system is designed for a new E-100-3.9-440 GM boiler made by Belenergomash-BZEM LLC. The boiler’s main parameters can be read from its designation under the GOST 3619-89 standard.
| Part of the designation | Meaning |
|---|---|
| E | natural circulation boiler, i.e. a drum boiler |
| 100 | rated steam output of 100 t/h |
| 3.9 | absolute steam pressure of 3.9 MPa |
| 440 | superheated steam temperature of 440 °C |
| GM | fuel: natural gas (G) and fuel oil (M, mazut) |
For a gas- and oil-fired drum boiler, the control platform usually runs several control loops: load and steam pressure through the fuel supply, the fuel-to-air ratio, furnace draught, the drum water level and the superheated steam temperature. Burner light-up, process protections and interlocks are separate functions: for example, if the flame goes out or the drum water level falls too low, the protections shut off the fuel. How such systems are designed and brought into operation is described in the process control systems section.
What we did
- Design
Application software on SIMATIC PCS7
Development of the application software for the steam boiler control system.
- Supply
Control cabinets
Supply and assembly of the system’s control cabinets.
- Testing
Factory acceptance tests
Testing of the control system on the test bench before shipment to site.
- Commissioning
Bringing into operation
Commissioning of the control system at the mill’s CHP plant.
The result
The application software has been designed, the control cabinets supplied and assembled, the factory tests passed; commissioning of the boiler control system was under way at the CHP plant.
Boiler tests and the manufacturer’s letter
At the end of 2023 the company’s specialists took part in the successful tests of the boiler at the Knauf Petroboard site, as stated by the boiler manufacturer, Belenergomash-BZEM LLC, in its letter No. 018-0042 of 5 February 2024. The letter also says: “We express our gratitude to the team of Energy Management LLC for the flexibility they showed and their readiness to look for solutions for the good of the project” (translated from Russian). The scan of the letter is on the letters of appreciation page, and a news item about the letter is in the news feed.
In the same letter, the boiler manufacturer looked forward to working together at the final stage of the plant’s operating mode tuning as well. During operating mode tuning, performance tests of the boiler are carried out and its operating mode chart is drawn up: target values of fuel and air pressure, oxygen content in the flue gas, furnace draught and steam temperature at different loads. For power plant boilers such tests are mandatory at commissioning, and the boiler is then operated to the approved chart (clause 243 of the Russian Rules for the Technical Operation of Power Plants and Networks). The company’s other work for power plants and pulp and paper mills is described on the power generation and pulp and paper industry pages.
Gallery


Equipment and services in this project
Similar projects

Ilim: board machine control system
board machine of 600 thousand tonnes a year · 2023

USC: electrical equipment for 3 fishing vessels
power distribution and monitoring system based on PMA300 · 2020–2023

Belenergo: 11 SGT-800 gas turbine units
11 × SGT-800 · full load in 15 minutes