What is a substation

A substation is an electrical installation for receiving, transforming and distributing electricity: power transformers, switchgear with circuit breakers and disconnectors, protection and automation. It is classified by its highest voltage — 110, 220, 330, 500 kV — and by the type of switchgear: air-insulated, indoor or GIS.

Key facts

  • Purpose: receiving, transforming and distributing electricity.
  • Classes by highest voltage: 110, 220, 330 and 500 kV.
  • Switchgear types: air-insulated (AIS), indoor and GIS.
  • GIS cuts the switchgear footprint 25–30 times.
  • Equipment is tested on site before energisation.

What it consists of

High- and low-voltage switchgear, power transformers or autotransformers, reactive compensation, auxiliaries, protection relays, emergency automation and the substation control system. Feeders — lines, transformers, bus-section and bus-coupler breakers — follow standard schemes: single or double busbar, bridge, breaker-and-a-half.

Types by switchgear design

Air-insulated switchgear (AIS) — apparatus in the open air, the cheapest but needing a large area and exposed to the climate. Indoor switchgear — apparatus in a building. GIS — all apparatus in sealed SF6-filled enclosures: 25–30 times less space, independence from the environment, service life over 50 years. Prefabricated modular substations are assembled and tested at the factory and only joined on site — 29 such modules were installed at Yamal LNG.

Voltage classes

110 kV substations serve distribution networks and industrial supply; 220 kV — nodal substations and large consumers; 330 and 500 kV — the backbone grid. Apparatus is selected by the highest voltage of the class (145, 245, 363 and 550 kV to IEC), rated current and breaking current.

Construction and energisation

The sequence: design, equipment supply, erection under the supplier’s supervision, on-site high-voltage tests, protection and automation commissioning, integrated trials and energisation. The test laboratory tests GIS, breakers and current and voltage transformers up to 750 kV before switching on.

Where it appears on this site

The 220 kV TsRP substation (Rosseti, Krasnoyarsk) — 1,920 sets of GIS equipment; the modular substations of Yamal LNG; high-voltage equipment service and the test laboratory for grid companies and industrial plants.

Questions and answers

How does a substation differ from switchgear?

Switchgear is part of a substation: the busbars, circuit breakers, disconnectors and current transformers of one voltage class. A substation includes several switchgear installations, power transformers, protection relays, auxiliaries and a control system. For example, a 220/110 kV substation has switchgear of two voltage classes linked by autotransformers.

What is a modular substation?

A substation built from factory-assembled modules: equipment is installed and tested at the factory, and on site the modules are only set in place and connected. This shortens construction in remote areas — 29 modular substations were installed at Yamal LNG.

Which tests are carried out before a substation is energised?

High-voltage withstand tests of GIS and breakers with partial discharge measurement, checks of current and voltage transformers, insulation and main-circuit resistance measurement, breaker characteristic checks and protection commissioning. The test laboratory then issues reports and a statement of readiness for energisation.

Related terms