What is a high-voltage withstand test

A high-voltage withstand test checks the insulation of electrical equipment with a voltage above the operating value for a specified time: the insulation must withstand it without breakdown or flashover. For GIS and breakers after erection an AC voltage is applied, usually 80 % of the factory test value, with simultaneous partial discharge measurement.

Key facts

  • Checks insulation with a voltage above service level for a set time.
  • Pass criterion: no breakdown or flashover.
  • On-site GIS tests use about 80 % of the factory test voltage.
  • Partial discharges are measured at the same time.
  • Reveals particles and assembly defects before energisation.

Why it is needed

Factory tests confirm manufacturing quality, but during transport and erection particles or moisture may enter GIS enclosures or joint defects may remain. The on-site test reveals them before the operating voltage is applied: a defect shows up as a breakdown during the test rather than as a fault in the network. For repaired equipment the test confirms that the insulation has been restored.

How it is carried out

The object is switched off and earthed, voltage transformers and surge arresters are disconnected, and the resonant test set is connected. The voltage is raised in steps: first conditioning at a reduced level so that particles move into the traps, then the hold at the test voltage — usually one minute. Partial discharges are measured during the hold; the result is recorded in the report. In case of breakdown the compartment is opened, the cause is found and removed and the test is repeated.

Voltage levels

The factory power-frequency test voltage for the 145 kV class is 275 kV, for 245 kV — 460 kV, for 550 kV — up to 740 kV; on site 80 % of these values is applied. Test voltages up to 750 kV are produced by the test laboratory’s mobile resonant systems.

What is tested

GIS and SF6 bus ducts, dead-tank and live-tank breakers, disconnectors and earthing switches, current and voltage transformers, cable lines and joints. The test laboratory issues a report and a statement of readiness for energisation.

Questions and answers

How does a withstand test differ from an insulation resistance test?

A megohmmeter measures insulation resistance at a low DC voltage and shows general moisture or contamination. A withstand test stresses the insulation above service voltage and reveals concentrated defects — particles, cracks, poor joints — that a resistance test cannot see.

What voltage is applied to GIS on site?

Usually 80 % of the factory one-minute power-frequency test voltage: about 220 kV for the 145 kV class and about 370 kV for 245 kV. Before the hold, the insulation is conditioned at a reduced voltage so that particles move into the traps.

What if the insulation fails the test?

The compartment is opened, the breakdown point is found, particles are removed or the damaged spacer is replaced; the compartment is reassembled, evacuated and filled with SF6, and the test is repeated. A defect found during the test costs far less than a failure in service. The report of the repeat test becomes part of the as-built documentation.

Related terms